There is no guess work in determining project
completion levels
By MUNGAI KIHANYA
The Sunday Nation
Nairobi,
24 January 2021
A recent news report
quoted the project manager of the Nairobi Western Bypass saying that the
construction was 43.9 per cent complete. A number of readers asked me to
comment on this figure: 43.9. It seemed too accurate.
The question that
these readers were asking about is how project completion levels are
worked out. Project managers monitor three distinct parameters, namely;
the duration expired since starting, the amount of money utilised and
the volume of work completed.
The duration expired
since starting is compared to the contract period and expressed as a
percentage. The unit of time is weeks – unless it is a very short
project lasting a few days. Thus, on the 45th week of a
52-week (one year) project, the manager can say that 86.5 per cent of
the time has elapsed. If the project exceeds the agreed period, then
this percentage will be above 100.
The money utilised is
based on total amounts claimed as the work is going on. Again, this
figure is expressed as a percentage of the total project cost. So, if
the total cost was Sh678,345,000 and the contractor has so far claimed
Sh123,789,000, then the manager can say that 18.2 per cent of the funds
have bee utilised.
Finally comes the
question of volume of completed works. In this case the project manager
looks at the tasks of the project that have been done and compares them
to total tasks in the entire project. However, some tasks are bigger
than others, so, how is the magnitude of a task assessed?
In the planning
stage, each task is identified and allocated a certain duration for
completion. So, as the work progresses, the manager records the
completed tasks and the budgeted time for each. These are then expressed
as a percentage of the total cumulative duration of all tasks.
It is important to
note here that the cumulative duration of tasks is not equal to the
project period! The reason is that some tasks are carried out
simultaneously. If three tasks are to be done together during one week,
their cumulative duration is three weeks.
Thus, if a project
has a cumulative duration of, say 6,892 weeks and the completed tasks
had been assigned 3,026 weeks, the manager can say that it is 43.9 per
cent complete.
My only criticism is
on quoting the number to three significant figures (43.9) while two
would have sufficed (44). But perhaps this project manager wanted the
public know that he was not guessing the level of completion.
|